Fax | 807-344-2977
Toll Free | 1-800-463-2249
reception@matawa.on.ca

RAPID LYNX PROVIDES AN UPDATE ON PROGRESS ON PHASES 1 AND 2 OF BROADBAND PROJECT AND ATTENDS INDIGENOUS CONNECTIVITY SUMMIT

MEDIA RELEASE

Tuesday, June 4, 2024 | FOR IMMEDIATE RELEASE

RAPID LYNX PROVIDES AN UPDATE ON PROGRESS ON PHASES 1 AND 2 OF BROADBAND PROJECT AND ATTENDS INDIGENOUS CONNECTIVITY SUMMIT

MEMBERTOU, NS: Further to reporting an overall 62% rate of completion of the Rapid Lynx Telecommunications (RLT) backbone network on April 30, 2023—RLT is providing a further update on the progress of the broadband project that began construction in 2020. The network will be the only long-haul fibre optic network in Ontario’s Far North, and it will be 100% owned, controlled, and operated by the Matawa First Nations.

To-date, the following has been completed in Phase 1:

  • 70% – including consults, engineering, and construction

To-date, the following has been completed in Phase 2:

  • 35% – including consults, engineering, and construction

A further update on RLT’s progress will be made at Matawa First Nation Management’s 36th Annual General Meeting (AGM) taking place in Neskantaga First Nation from July 31 – August 1, 2024 (the AGM will also be livestreamed).

This week, RLT will be participating with other Indigenous broadband companies from both Canada and the United States at the Indigenous Connectivity Summit in Membertou, Nova Scotia including a panel discussion this morning.

– 30 –

For more information, please contact: Carol Audet, Communications Manager – Matawa First Nations at (807) 632-9663 or (807)646-6505 or by email at caudet@matawa.on.ca.

DOWNLOAD MEDIA RELEASE

Phase 1 involves connections between Eabametoong, Marten Falls, Nibinamik, Webequie First Nations with interconnection at Aroland First Nation. Phase 2 began in 2022 and involves connections between Aroland, Constance Lake, Ginoogaming and Long Lake #58 First Nations.